What’s Gone Wrong With the LAX People Mover


We’ve talked about why the SkyLink people mover at LAX is so important, and exactly what it will look like. But as nice is it is to talk about that, it’s time to get down and dirty in the mud. We have a lawsuit filed by the consortium of contractors on this project, LINXS, against the City of Los Angeles which runs LAX through Los Angeles World Airports (LAWA). So now we get look under the hood and see what’s going on.

This lawsuit has been in the works for a long time. The rules for suing Los Angeles required you to file a government claim before you sue. The city can either accept the claim, reject it, or do nothing. There was no chance the city was going to accept this. If it did nothing for 45 days, then a two-year window would open during which LINXS could sue the city. LA did not do that. It outright rejected the claim on January 21 of this year. When that happened, LINXS had a six-month window open to sue. It waited until the end of that window, but it did file what I assume will be the first of many lawsuits on July 9. (If you’d like to follow along, you can search the docket at the LA Superior Court using case number 26TRCV02456.)

So what is LINXS’s beef? If only there was just one issue. LINXS has a laundry list of complaints, so we might as well talk through them all if, for no other reason, just for the sheer entertainment value.

The Problematic Metering Cabinet

Connecting the people mover with electricity is a very complicated process. There are sub-stations which receive power through LA’s Department of Water and Power (DWP), and then at some point there is a join where DWP’s work meets LINXS’s. There are metering cabinets in multiple places which measure the usage, just like at your house.

One of these metering cabinets has become a flashpoint. According to the lawsuit, these metering cabinets were not in scope for LINXS to design, build or really do anything, yet it seems that LINXS (“Developer” in the lawsuit) actually did the work anyway for some reason. Here’s how the lawsuit says it:

LAWA has alleged that Developer procured the Metering Cabinets at issue from Pioneer Power Solutions and had them installed, but, in any event, the Metering Cabinets were not in Developer’s contractual scope of Work.

I find it very funny that LINXS says LAWA has alleged this, but it doesn’t confirm it nor does it deny. It just says it doesn’t matter if LINXS did the work, because it wasn’t supposed to. That’s… a strategy.

Anyway, DWP screwed up, as those who live in Los Angeles won’t be surprised to hear. They didn’t have big enough cables to provide electricity, so in September 2024 they fixed the problem which required going into the metering cabinet to connect the cables. Apparently “within days,” the metering cabinet failed.

In January 2025, DWP apparently heard a noise coming from the cabinet, so it opened it up and found “moisture and debris” in there. Now, LINXS says this could have only happened when DWP opened it up to fix the cables. Why? Because DWP locked the cabinet and didn’t give LINXS a key. Apparently, LINXS doesn’t think it’s possible that this could have been manufactured or installed wrong, assuming it would admit it actually did install it in the first place.

Meanwhile, DWP had to cut power from February to July 2025 to allow — wait for it — LINXS to fix the thing, so LINXS thought it deserved a project completion date extension. LAWA said no, and because of that, it could withhold a $115 million progress payment. I won’t get into the weeds on why, but as you can imagine, LINXS doesn’t like that one bit.

This dispute went to what’s called a “project neutral,” who is supposed to quickly help settle disputes. The project neutral agreed with LINXS, but it turns out, the project neutral has never once agreed with LAWA. It sounds like this person may not be so neutral. (For more on this, I highly recommend watching this video.)

As if that’s not enough, LINXS says that it has uncovered that LAWA knew this was DWP’s fault the whole time and it was a big cover up.

So, that’s… one issue.

Other Contractors Ruin Everything

LINXS has been working in its project area at LAX for many, many years now. As the years go by, more unrelated projects need to get started in that area, but LINXS says they should all stay out of the way. They aren’t doing that. Even more than that, LINXS goes dramatic by saying some of its work has been destroyed. What happened? Apparently some work by other contractors on 96th St resulted in “damaged Developer installed irrigation lines and valves, as well as planters, shrubs and trees.”

Sounds a lot less dramatic that way, huh? And also, I will point out, this is landscaping. How this prevents them from running a train, I have no idea. But wait, there’s more. See, these contractors working in the LINXS project area is a safety issue. And yes, something has happened.

“…one of LAWA’s Other Contractors, in the process of demolishing a glass lighting pylon, ejected shards of thick glass plate onto the guideway over which the People Mover vehicles travel. Fortunately, no workers were on the tracks at the time, and the vehicles were not being tested in the area showered by glass.

Right, well, I’m going to assume that this other contractor probably made sure nobody was around when it decided to demolish a glass pylon. LINXS seems to want to use this as leverage by now slowing down other projects to run as slowly as its own.

Oh, and I almost forgot another favorite. LINXS says other contractors are stealing its electrical power! Sounds like someone needs to talk to DWP.

The Drawing Scandal

A sub-contractor for LINXS submitted some drawings to the city for approval for some roadway construction work. And then, SCANDAL.

According to LINXS, somebody “altered and resubmitted” these drawings and “deleted certain elements of the roadway work….” Wanna guess who LINXS blames? That’s right, it says LAWA did it. But why?

Developer is informed and believes, and based on that information and belief alleges, that LAWA was behind the resubmission of the [engineer’s] roadway drawings, and the purpose was to obtain permits for a reduced scope of roadway work so that LAWA could attempt to declare (wrongfully) that Developer’s work in certain areas is complete, such that LAWA’s Other Contractors could work in those areas.

So, LAWA wants to reduce the scope and help the project reach completion faster, but now LINXS doesn’t want that? Make up your mind, people. Do you want to finish this thing or not?

But wait, there’s more. Because the updated drawings still had the original engineer’s seal and signature, LINXS says this is now a criminal issue.

Don’t Be a Blocker

LINXS says that LAWA is blocking simple things, and that’s preventing the project from being finished. This is like two kids fighting.

  • There is a solar farm which will power the people mover but also send power back to the grid. To connect this with DWP, “the customer” needs to sign a document. LINXS says LAWA needs to sign, but LAWA says LINXS needs to sign.
  • LINXS is supposed to be doing some street/landscape work which includes installing irrigation. LINXS says it did that, but it had no responsibility after building it. The work is done, but LAWA never applied to DWP to turn on the irrigation.
  • There was a requirement that LINXS put together a cybersecurity plan. It did that, and then it submitted some modifications which it called minor clarifications. LAWA said the intrusion detection system was removed, but LINXS said that didn’t happen. Oh, and crucially, “LAWA complained that a word was missing at the end of a sentence that was unrelated to the substance of the [plan].”
  • LINXS submitted a test plan for a surveillance system. LAWA said it had issues with it, but LINXS said that’s crap.

Clock’s a Tickin’

So, here we are. And while they fight this out over some seemingly stupid things — just look at how many of these actually involve the SkyLink train itself — the clock is ticking.

If LINXS doesn’t have this thing ready by October 8, then lenders can call the loan. While it doesn’t definitively say so, the implication is clear. LINXS will go bankrupt, and it wants LAWA to know that will be bad news for LAWA. As of now, the projected opening date is November, so, uh, something’s gotta give.

See, if LINXS goes bankrupt, then LAWA will apparently have to pay a ~$900 million termination payment, and the airport will have to find a new operator which LINXS says will cost a lot more. Why would a new operator be needed? Well, this is a deal that spans decades and includes the actual operation of the people mover for many years to come, not just its construction.

If this all sounds bad, just wait. LINXS has already submitted another batch of government claims on June 5, and these were rejected by the city on July 7. So, the six month clock is now ticking for a whole new round of lawsuits.

Meanwhile, millions of travelers have to sit there and wait just to get a damn train.

Get Cranky in Your Inbox!

The airline industry moves fast. Sign up and get every Cranky post in your inbox for free.

Brett Avatar

56 responses to “What’s Gone Wrong With the LAX People Mover”

  1. Brad Avatar
    Brad

    Yeah, getting in, out and around at LAX and the area is a crapshoot. Some days it is barely tolerable and other days it is a total disaster. This thing was needed years (decades!) ago.

    But, that aside, this is how lawsuits work, you don’t start with a reasonable position, the lawyers throw every little thing at the wall to see what will stick, and every little thing is almost always exaggerated as much as they think they can get away with without the judge just going, “um, nope.”

    There is also some PR value in these lawsuits, they know it will be covered in the news (such as it is today) and they’re also trying to sway public opinion from the get go to bolster their position and standing in the community.

    So here we have it, we’ll either figure out what the actual issues are in a few years OR they’ll settle this thing (most likely outcome) and we’ll never know who gave in on what issues.

    1. Matt D Avatar
      Matt D

      It’s pretty sad (and scary) to think that the court of public opinion can have as much-perhaps even more-influence and power than an actual court of law.

      1. SEAN Avatar
        SEAN

        It does. In fact, the difference is that a court of law can’t turn on you & cause you to lose the next election. But the court of public opinion certainly can & you are starting to see that occur more.

  2. Bill from DC Avatar
    Bill from DC

    Great analysis Brett. Even though my days as a LAX frequent flyer date back to when the now demolished T5 was the newest, shiniest terminal not named after a former mayor, this still makes my head hurt.

    The only bottom lines are that people still can’t get on the (alleged) people movers and that scores of attorneys are getting rich(er). If you really want to torture yourself, see if you can add up the legal fees!

  3. Horace Greeley Avatar
    Horace Greeley

    It’s LA of course

    1. 1990 Avatar
      1990

      Eh, petty contract disputes aren’t just in Los Angeles, or California, or only ‘blue’ cities and states, etc. There’s ample funny-business going on everywhere. Check the front of the NYTimes website right now. Headline article on the administration halting the Federal Transit Administration’s Capital Investment Grants program, leaving more than $7 billion in voter-approved and congressionally budgeted federal transit money unspent. Basically, those in-charge at the moment seem to loathe anything trains, rail, buses, mass transit, etc. (unless there’s a grifting opportunity, but, crypto is probably much easier than hard, big, physical infrastructure, clearly.) They’d really prefer you just drive, or be driven (ride-share), perhaps. Those without means, be darned! So, there’s that, too. *gulp*

      1. Brian W Avatar
        Brian W

        Let’s see if the new SLC or CMH airports has/have the same contract issues, overruns, and delays as LAWA has experienced.

        1. Lucas Avatar
          Lucas

          Or the PDX expansion

        2. 1990 Avatar
          1990

          Pardon my NYC focus, but I’ll be happy as a clam if any of the new JFK terminals partially open this year (expecting the new T1, T6/7); in-full, supposed to take until 2030.

          1. SEAN Avatar
            SEAN

            knowing the PANYNJ, it will take that long & then announce a massive terminal redevelopment that will take another decade plus to complete. By that time the Yankees & Knicks will each win another title.

            1. 1990 Avatar
              1990

              Me like-y this comparison. Now, if the Yankees and Knicks can pulls that off, that would not be too bad. Like, 10+ vs. waiting another 53 years; of course, Yankees (’09) are overdue, but some would say they’ve won enough already (27x). Now, if the Mets (’86) or Jets (’69) or Nets (never) win a championship before the new JFK is done… now, that’d be… a small miracle.

  4. Alan Z Avatar
    Alan Z

    Well, after reading and careful re-reading, I established one clear fact, this project is neck and neck with the opening of the new Berlin airport. The other observation is that too much money was spent. If only Shakespeare was here to give his salient advice.

    1. 1990 Avatar
      1990

      C’mon, William, not the ‘good’ ones! …

      And, at least with BER, the delays were *mostly* actual engineering and fire-safety system failures (right? RIGHT??) Here, the physical train and tracks are built and ready; this is just contractors fighting over money.

    2. Seanny Avatar
      Seanny

      As much as people don’t like the silo-ed terminal design at LAX, this debacle is an argument for why it’s better to let the airlines (Delta, American, possibly United one day) manage the contracts for terminal upgrades.

      1. Annieairplane Avatar
        Annieairplane

        The major airlines do manage terminal upgrades for exclusive (or primarily) use terminals at LAX. It is complicated as there are many levels of approval and the funding process is complex, but AA, DL, UA, and WN have all had direct management of their terminal projects.

  5. RemingtonSteeleDossier Avatar
    RemingtonSteeleDossier

    I should have mentioned this after Part 1, but that map desperately needs a Godzilla between the CONRAC and the horseshoe.

    1. Bill from DC Avatar
      Bill from DC

      Great idea but we need the LA equivalent! After originally suggesting earthquakes or other natural disasters, when pressed to come up with a single Godzilla equivalent, Gemini replied, “If you want a single, concrete, canonical beast to serve as the direct counterpart to Godzilla for Los Angeles, the ultimate answer is the Giant Mutant Ant Queen from the 1954 sci-fi masterpiece Them! If Godzilla is Tokyo’s definitive monster, the Ant Queen is the definitive beast of Los Angeles.”

      Personally I would choose the giant donut from nearby Randy’s Donuts:

      https://www.gettyimages.com/detail/news-photo/1990s-america-randys-donuts-inglewood-california-1991-news-photo/1354408282

      Nothing says, “don’t rush, it won’t get you there any faster!” better than a gigantic donut. Perhaps bringing it to life as an evil entity such as the Stay Puft marshmallow man from Ghostbusters would work?

      1. Oliver Avatar
        Oliver

        King Kong? (I assume it’s a Hollywood native)

      2. Ian Avatar

        Randy’s Donuts was already iconic and then a space shuttle stopped there and added to the legend. https://commons.wikimedia.org/wiki/File:Space_Shuttle_Endeavour_at_Randy%27s_Donuts.jpg

        As for the people mover line, artists could be commissioned to put up replicas alongside the line with all manner of LA and Hollywood icons including the donut, space shuttle and probably a miniature Hollywood sign, just for starters. Make sure they keep hearing the idea.

    2. Southside Emil Avatar
      Southside Emil

      Agree. Bring in Godzilla

  6. Hov Avatar
    Hov

    Having just renovated my condo, if this thing goes to trial I absolutely would not be able to be an unbiased juror. Contractors can turn a reasonable human into a crazy maniac with their delays, mansplaining, denials, explanations that defy reason, and downright indifference at times.

    Here’s hoping this thing gets fixed.
    Also HOW could the city’s lawyers leave the city on the hook for near $1 billion if the developer goes bankrupt?!?! Why is it the city’s fault if developer doesn’t manage their finances properly???

    1. SEAN Avatar
      SEAN

      It’s the teenager gets caught drinking by police, but parents are held responsible situation. I’ll leave it up to you to decide who is who.

    2. Brett Avatar

      Hov – That’s just what the lawsuit alleges LAWA would have to pay. LA may have a different interpretation of how that works, but I really don’t know. I’ve reached out to LAWA to get some answers, but since this is an active lawsuit, I’m not holding my breath.

    3. Brian w Avatar
      Brian w

      I would love to know how LAWA which has experience with major construction projects, was so inept writing this contract to protect the taxpayer. At minimum they could have forced LINXS to buy insurance to cover their cost their bankruptcy.

      1. Brad Avatar
        Brad

        When I was on a city council (a gnat in size compared to LA and also not in CA) we always required contractors post a bond (a form of insurance) for some standard percentage of the contract final price, if they failed to deliver or left loose ends, we could call some or all of the bond to have the project completed to our satisfaction.

        Trust me, when I say that NO contractor wants the bond called (unless they’ve already gone out of business) – they basically buy insurance to cover the bond cost and if they get one called all their future bonds cost more to procure. It is a good tool to ensure that projects are completed fully and to the client’s reasonable satisfaction within the scope of the contract.

    4. Seanny Avatar
      Seanny

      I think both the City and the Contractor would be pretty foolish to let this go to trial, but then again, it seems like both are willing to risk it. Enough to make one long for the days of Mulholland.

  7. SEAN Avatar
    SEAN

    This is what happens when PPP’s go absolutely wrong! The MTA in NYC has a similar problem with the handful of contractors they use & don’t get me started with the huge number of consultants on every large job.

    1. 1990 Avatar
      1990

      *sigh* Yup. P3s are sold as a way to transfer risk away from taxpayers, but in practice, they just create a legal way for every minor design or utility hiccup to turn into a breach-of-contract lawsuit. When the P3 has all the leverage, the public just gets stuck with the delays and the bill. *cries in 2nd Avenue Subway* (Don’t worry, maybe by the 2050s!)

      1. Brian W Avatar
        Brian W

        It is all how the contract is written and enforced. The new SLC Airport was built quicker than the LAX people mover.

        1. 1990 Avatar
          1990

          And the new SLC airport is glorious, indeed. Incredible new lounges (and rental car center) as well. Then again, very different surrounding area. Like, let’s just say, real estate is not as much at a ‘premium’ at the edge of the literal lake that smells of ‘rotten eggs.’

          1. Brian W Avatar
            Brian W

            The people mover is just a 2 mile elevated light rail. While it is in congested space, it is outside terminal and taxiways. The SLC airport cost $5.1B and the LA people mover cost about half the price of the SLC airport to build.

            1. 1990 Avatar
              1990

              I get that they’re both airports and people-movers, but they are sorta different beasts. Regardless, I think the new SLC deserves a lot of praise.

              The further irony is that Utah, logistically, is gonna be ready for its next Olympics (2034) before Los Angeles (2028).

  8. Rowdy Yates Avatar
    Rowdy Yates

    It is unfortunate that just about every project at LAX since the upper level roadway in 1983 has had lawsuits by the contractors. The LAX lawyers review the previous contract and try to learn from mistakes, but the contractors always have better lawyers and find new loopholes to make more profit at our expense.

    1. Brad Avatar
      Brad

      At some point, the common denominator really does point to the problem, and somewhere in the last 43 years it would seem that that point was reached.

      I’d suggest that the amount of money that LAX/LAWA spends on legal help should be getting them competent representation.

    2. Brian W Avatar
      Brian W

      From reviews I have seen online, LAWA laywers failed “bigly” without including basic protections for provisions regarding appeals and mediation. LAWA didnt demand a mediation board or have a mechanism to remove a mediator it felt was biased.

      1. Brett Avatar

        Brian W – Yes, they definitely screwed that up and it was mentioned in the grand jury report that was referenced in the video I linked to. They just have the one project neutral who has never ruled in their favor which would presumably mean there’s a real bias there. And they can’t do anything about it except just move on to the next level which slows everything down.

  9. 1990 Avatar
    1990

    Another LAX People Mover post? Now THIS is a good start to the week!

    This lawsuit proves that LAX’s issue isn’t about state politics; it’s just a pretty silly contractual dispute and a bunch of drama-mamas. If I’m reading it correctly, a single missing word in a cybersecurity sentence and some large egos at a municipal department are all that’s standing between passengers and a functioning airport link?

    Grr. If so, that makes me even more miffed that this isn’t ready in time for my upcoming trip to LA… and, if that October lender deadline triggers a $900M bankruptcy reset, ‘ready by 2028’ might actually be optimistic.

    Nevertheless, I look forward to re-hashing all the same arguments as the prior post. Round-two!

    1. Brett Avatar

      1990 – Well that was one of the issues in the cybersecurity plan, apparently a missed word. I don’t know why LINXS wouldn’t just fix the word, but I’m guessing this is just adding a little bit of kindling on top of a roaring fire already. There are bigger issues than that, they’re just throwing it all out there.

  10. Doug Swalen Avatar
    Doug Swalen

    Left out of this summary, but it’s mentioned quite a bit in the video Brett referenced, is the contract between LAWA and LINXS which is a major contributor to why things are where they are right now, regardless of the claims and counterclaims. LAWA’s and the City Of Los Angeles’ lawyers should all be fired for allowing a contract like that be finalized. They have nobody but themselves to blame if the other party is a rather unscrupulous SOB that’s willing to use every avenue afforded by the contract to stick it to LAWA and the City.

    1. Brad Avatar
      Brad

      Easy to point the finger at the lawyers, but in the case of LAWA and the City of Los Angeles, it is highly unlikely that they had anything close to final say, they just worked out the legal words as best as they could under the circumstances.

      Don’t forget that either the politicians (city council) or the LAWA Board (or both) had to sign off on this mess. That alone brings a whole new level of drama into the equation.

      My home airport (DEN) desperately needs the road to the airport expanded, but the FAA will only pay for a little of it because most of it serves things other than the airport and the FAA only pays for direct airport related stuff, so queue up the Denver City Council to have a say. Those geniuses on the Denver City Council desperately want bike lanes added to Pena Blvd so you can ride your bike with whatever luggage/carry on stuff you have the 26 miles from downtown Denver to the airport and they’d rather not expand the actual road for those nasty polluting vehicles at all. All they have done so far is authorize a study on what to do which will take years while the traffic congestion gets worse by the month.

      So, step back and see what the politicians in LA were doing on this project and whose campaign donations were bolstered by said LINXS outfit before the contract was signed. They may be long gone from office due to the timeline here, but…

      1. Doug Swalen Avatar
        Doug Swalen

        “Don’t forget that either the politicians (city council) or the LAWA Board (or both) had to sign off on this mess. That alone brings a whole new level of drama into the equation”

        I very much doubt the politicians did a line by line read-through of the contract though. That’s the lawyers’ job. And they blew it, either by missing those clauses which have allowed LINXS to run wild as well as allowed for a clearly biased mediator to stay on the job without any mitigation, or by not missing them and agreeing to it without thinking about the possible ramifications of leaving that language intact. Either way the lawyers failed their clients…unless the lawyers warned against this language and the politicians overrode them…which seems a rather far-fetched scenario to me because there was no upside and only downside in leaving that language in place.

        We can question the politicians motives, some of whom are no longer there. The replacement of the Eastern span of my San Francisco Oakland Bay Bridge was held up for years and came in very late and overbudget with what turned out to be a bad design because of political interference and don’t get me started on the BART to San Jose boondoggle. So you have ample reason to be skeptical of the politician’s motives. But no politician is going to deliberately agree to something that contractually and legally ties their hands like that. They pay lawyers to prevent that from happening.

        1. Brad Avatar
          Brad

          Doug,

          I mostly agree with you, but I’ve seen enough shenanigan’s to have some real suspicion when things go this badly. And of course no city council person has read line by line contracts like this, unless they are a lawyer it really wouldn’t be worth the time to do that – but they should have a good grasp of how the contract works and what the risk areas are so they can properly decide if they organization they represent wishes to take on that risk.

          It would be interesting (but way too time consuming) to go back and read the official records of these meetings to see just what the politicians were comfortable doing. Of course, nobody says in public that “they are friends” with someone on the project team, but they might ask the lawyers, “is this really necessary?” when it comes to some of the clauses.

          The brief descriptions of some of these failings suggest that the lawyers committed malpractice, and should perhaps lose their license to practice law, in allowing some of these things to be in a final contract, UNLESS someone signing the contract told them to.

          I was on City Council for a tiny little city for six years (no airport, no big contracts like THIS) and I was always keenly aware of what the lawyers had to say about things at our place, nobody ever went against the legal advice, but I saw other governments where that happened on a somewhat regular basis. Unfortunately.

          Final thought: if the client is ignoring the lawyers regularly, which lawyers are likely to be doing that work?

    2. Brian W Avatar
      Brian W

      I agree that LAWA’s lawyers were a failure. It is crazy to read LAWA has no authority to replace mediators it feels are biased and didnt require a mediation/appeals board. You would think there are basic legal templates for large construction projects that have strong taxpayer protections. I doubt LAWA will hold any of its staff accountable for this mess.

  11. Eric R Avatar
    Eric R

    Everything at LAX is “Frankensteined” together.

    The north end of the concourse never has been completed under the potential taxiway realignment. That excuse was BS from day 1 because it would have also reduced the T1-T3 footprint, and that never would have been realistic.

    Similarly, the south end of the new international concourse was patchworked together because of the AA hanger issue.

    LAWA is a classic case of bureaucracy at its finest. Too many people in the room with their own interests that have the ability to sway decisions rather than LAWA making decisions in the best interests of the airport itself.

    1. Brian W Avatar
      Brian W

      LAX has had constant renovation and additions for decades. Unless you are going to rip it down and start over, it is hard to develop a coherent flow. I dont fault LAWA for that.

      1. Eric R Avatar
        Eric R

        Both TBIT examples I used had zero to do with what you are suggesting though.

        The north end of the main TBIT terminal due to non-sense around potential taxiway realignment, and the south end of the new TBIT terminal due to years of indecision and bickering around the AA hanger.

        Too many people with their own interests that carry too much influence. Ultimately it detracts from the overall good of the airport.

        1. Darin Avatar
          Darin

          Your characterization of the TBIT south end development is either partially correct, or completely incorrect. Not sure.

  12. Patrick Avatar
    Patrick

    While everybody cries over the situation with the Peoplemover mess at LAX they seem to overlook an easy solution…..BUR, SNA, LGB, and ONT are all in the vicinity and probably less problematic for those looking to fly in and out of the area.

  13. haolenate Avatar
    haolenate

    is LINXS in charge of the CA high speed rail project too?

    I wonder what we’ll see first…. the SF/LA high speed line, Brightline from Vegas to *almost* LA, or the LAX People mover operating.

    1. 1990 Avatar
      1990

      We could also set even lower expectations. Like, what if none of them are finished, and all of them are just abandoned… like those three “Graffiti Towers” in Downtown Los Angeles (Oceanwide Plaza?) We got a few in NYC, too. Like, there’s one in Tribeca with ‘RAMS’ tagged on the top. Then, there’s one in the South Seaport area that’s a leaning-tower. Yeah, see, it can be far worse than just delayed and overpriced.

        1. 1990 Avatar
          1990

          Nice!! I can only hope they pull-off something similar for our graffiti towers in NYC.

  14. NVU Avatar
    NVU

    Does anyone remember how the O’Hare people mover was closed for four years from 2018-2022 while the 300 yard extension they started building in 2015 was “tested”? That project also involved massive cost overruns, years of delay, and litigation as well. Any other airports considering a land side people mover should run in the opposite direction.

    1. 1990 Avatar
      1990

      Yes, I remember (and had mentioned the ATS issue in a comment on Brett’s other recent post about LAX). The frustrating thing about ORD’s was that it was only supposed to be closed for mere months in 2019; then 3 freaking years later…. let’s just say, the over-crowded buses to T5 were not ‘great.’

  15. Aaron Avatar
    Aaron

    So I am reading about the fight here between LAWA and LINXS and it reminds me very much of the fight between WMATA (Washington DC Metro) and MWAA (Metro Washington Airport Authority) to build the Silver Line (to IAD from DC). Obviously WMATA will operate the line, as it will use Metro subway cars and interline into the rest of the sytem etc. But MWAA was the one given the money / contract to build it, and I’m sure WMATA was upset about it. So the stations / tracks needed to get built and then handed over to WMATA for operation. And WMATA redlined SO much of it – PA speakers not loud enough, concrete panels cracking, etc. etc. etc. It was ridiculous how long some of the handover was taking that people were pretty sure that this was WMATAs way of striking back for not getting the contract

  16. Anton Avatar

    Excellent article. Pretty much agrees with the analysis of nandert on YouTube. I saw the People Mover moving around the tracks today (2026-Aug-02), but it looked like more “testing” because I didn’t see any people using it.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.